A complete set of implementation plan for a weak electrical room, template material

ForewordHello, I am Mr. Lin, computer room remodeling plan, computer room refurbishment project should provide a detailed implementation plan, share it today, this can be used as a plan template, simple modification. It can be used in one click. TextChapter 1 Transition instructions

1.1 Transition goals

With this transition, you can implement following functions:

1. A certain project needs to perform a disaster recovery for a bank in order to prevent inconvenience to users in jurisdiction as a result of natural disasters.

2. This migration only performs disaster recovery migration and user hardware setup. The operation is planned to be carried out on May 12, 2020 and to guarantee duty next day (see schedule for specific time).

3. After switching, change network structure according to user's requirements without changing original user's requirements, and apply all security policies of source equipment to new equipment according to user's requirements.

4. This transition only configures original policy, and new user needs are not included in this transition, such as adding two aggregation devices.

1.2 Jump area

The equipment involved in this transition is Sangfor flow control equipment for export, and location of equipment is as follows:

Device location

Device model

The original computer room

sw1

The original computer room

sw2

The original computer room

sw3

The original computer room

sw4

The original computer room

sw5

The original computer room

sw6

The original computer room

sw7

The original computer room

R1

The original computer room

R2

1.3 Going online

The network connection of devices involved in this switchover is shown in figure below:

A complete set of implementation plan for a weak electrical room, template material

Original topology map (user provided)

A complete set of implementation plan for a weak electrical room, template material

Topology after conversion (user provided)

1.4 Switching equipment

Source hardware: R1, R2, sw1, sw2, sw3, sw4, sw5, sw6, sw7

New device: new1, new2

The original equipment R2, sw2, sw6 and sw7 is supposed to be moved to new computer room, and new equipment new1 and new2 will be added as aggregation equipment

1.5 Control address

The control address is shown in table below:

Device name

Address management

Exit R1

192.168.19.11

Exit R2

192.168.19.12

Main switch: sw1

192.168.19.21

Main switch: sw2

192.168.19.22

Access switch: sw3

192.168.19.41

Access switch: sw4

192.168.19.42

Access switch: sw5

192.168.19.43

Access switch: sw6

192.168.19.44

Access switch: sw7

192.168.19.45

Aggregation switch: new1

192.168.19.31

Aggregation switch: new2

192.168.19.32

1.6 Internet List

See following table for device connection information:

Local Device

Local port

Periodic device

Peer port

Vlan

R1

f0/1

sw1

f1/0

R2

f0/1

sw2

f1/0

sw1

f1/0

R1

f0/1

f1/1

new1

f1/0

f1/2

sw2

f1/2

trunk

sw2

f1/0

R2

f0/1

f1/1

new2

f1/0

f1/2

sw1

f1/2

trunk

sw3

f1/0

new1

f1/1

10

sw4

f1/0

new1

f1/2

10

sw5

f1/0

new1

f1/3

10

sw6

f1/0

new2

f1/1

20

sw7

f1/0

new2

f1/2

20

new1

f1/0

sw1

f1/1

f1/1

sw3

f1/0

10

f1/2

sw4

f1/0

10

f1/3

sw5

f1/0

10

f1/4

new2

f1/4

trunk

new2

f1/0

sw2

f1/1

f1/1

sw6

f1/0

20

f1/2

sw7

f1/0

20

f1/4

new1

f1/4

trunk

,,,,,,,,,,,,,,,,,,,,,,,

1.7 Deployment changes

Add new1 aggregation between sw1 source core switch and sw3, sw4, sw5 access, and add new2 aggregation between sw2 source core switch and sw6, sw7 access.

1.7.1 Source equipment configuration method

Initial R1 routing configuration

A complete set of implementation plan for a weak electrical room, template material

R1 PAT initial configuration

A complete set of implementation plan for a weak electrical room, template material

Initial R2 Routing Configuration

A complete set of implementation plan for a weak electrical room, template material

R2 PAT initial configuration

A complete set of implementation plan for a weak electrical room, template material

Switch vlan sw3 information

A complete set of implementation plan for a weak electrical room, template material

Switch vlan sw4 information

A complete set of implementation plan for a weak electrical room, template material

Switch vlan sw4 information

A complete set of implementation plan for a weak electrical room, template material

Switch vlan sw6 information

A complete set of implementation plan for a weak electrical room, template material

Toggle sw7 vlan information

A complete set of implementation plan for a weak electrical room, template material
1.7.2 Aggregation switch configuration

1. Adjust according to following table:

Number

Configuration content

Operator

1

Set Routing

2

Install vrrp

3

Install a trunk link

4

Install Layer 3 Interface

2. Here is configuration result:

A complete set of implementation plan for a weak electrical room, template material

Fig. 1. new1 routing settings

A complete set of implementation plan for a weak electrical room, template material

Figure 2. New1 vrrp settings

A complete set of implementation plan for a weak electrical room, template material

Fig. 3. Channel parameters new1

A complete set of implementation plan for a weak electrical room, template material

Fig. 4. New1 third-level interface settings

A complete set of implementation plan for a weak electrical room, template material

Fig. 5. Routing options new2

A complete set of implementation plan for a weak electrical room, template material

Fig. 6. New2 vrrp settings

A complete set of implementation plan for a weak electrical room, template material

Fig. 7. New2 trunk settings

A complete set of implementation plan for a weak electrical room, template material

Fig. 8. Interface settings new2 level 3

Chapter 2 Transition Plan

2.1 Schedule

The switching schedule is shown in table below:

Time

Work Content

Operator

14:00~18:00

Check and verify device's original configuration

14:30~15:30

Initial network environment test

15:30~16:30

New devices are already on shelves

16:30~16:50

Check configuration for new devices

16:50~17:10

Move equipment to new computer room

17:10~17:30

Transition

17:30~17:35

External network testing is normal, otherwise deselect

17:35~17:50

Check that policy and traffic are OK after switch

18:00~19:00

View and verify aggregation switch configuration

19:30~07:30 next day

Protecting your phone

Next day 07:30~16:30

Guarantee of duty on site

,,,,,,,,,,,,,,,,,,,,,,,,,

2.2 Staff contact form

The contact list of company personnel involved in this transition is as follows:

People

Phone

Roles and responsibilities

Project interface employee

Project staff

The contact list of construction company (someone) involved in this transition is as follows:

People

Phone

Roles and responsibilities

On-site project manager responsible for coordination

Implementation Engineer Responsible for Switchover and Warranty

2.3 Switchover Plan

A detailed plan for this transition is shown in table below:

Steps

Time

Work Content

Scale of business impact

Operator

Estimated time

1. Switching flow control device

Initial device configuration

The day before switchover

Check device configuration

No effect

1 day

14:00–14:30

Business testing and device configuration file backup before switching

No effect

30 minutes

Initial network environment test

14:30–14:40

Testing in an external network

No effect

2.5 hours

14:40–16:50

Check connectivity of intranet devices

No effect

16:50–17:00

Check configuration

No effect

Mobile

17:00–17:40

Move device to new computer room

No effect

40

Turn on device and turn it on

17:40–17:50

Installing aggregation devices on a rack

No effect

10 minutes

Device line switching

17:50–18:00

Connect cables according to design topology

All internet outages

10 minutes

Business test after transition

18:00–19:00

Performing business function testing, basic equipment connection testing, and monitoring status of equipment operation

All internet outages

60 minutes

Device Backup Switch

19:00–19:15

Close existing aggregation interface and restore original state.

All internet outages

15 minutes

Second, logistics support

Duty Guarantee

19:30~07:30

A standby phone guarantees stable network operation.

There are anomalous risks in business, you need to pay attention

12 hours

Duty Guarantee

07:30~16:30

Engineers are on site to ensure stable operation of network.

There are anomalous risks in business, you need to pay attention

8 hours

2.4 Switchover process 2.4.1 Preparing switchover configuration file

ØPrerequisites: Take offline screenshots of each device configuration for backup at least one day before switchover.

Number

Content preparation

Preparing results

1

Take a screenshot of configuration of device running on real network, take a screenshot of configuration of aggregation device offline, verify that it is correct, and save it for later use.

Finished

2.4.2 Checking Internet service before switching

ØRequired conditions: all devices are in normal operation and connection, and switch must be completed 30 minutes before switch and recorded for comparison with test results after switch.

Number

Test Content

Test results

1

Intranet test: web test, multiple test update

Baidu, Sina, Netease, Sohu

√Pass □Fail

2

Chat software test: QQ login test WeChat chat test

√Pass □Fail

3

P2P software test: a, Thunder

b, emule

√Pass □Fail

4

Test download speed: http download test

Thunder Boot Test

√Pass □Fail

5

Streaming media test: Youku test

LeTV test

√Pass □Fail

6

User Group Network Speed ​​Test: Leader Group, Information Group, Security Group

Security group, general group

√Pass □Fail

,,,,,,,,

2.4.3 Connection test before switching

ØSet conditions:All devices are in normal operation and connection status Use PC 192.168.10.1 to perform a PING test according to table below 30 minutes before switchover and record for comparison with test results after switchover.

Number

IP address

Test results

1

192.168.10.103

√pass □no pass

2

192.168.10.104

√pass □no pass

3

192.168.20.103

√Pass □No

2.4.4 Check after switching 2.4.4.1 Check equipment connection

After transfer is completed, engineer will check equipment connection according to following table:

Number

IP address

Test results

1

192.168.10.103

√pass □no pass

2

192.168.10.104

√pass □no pass

3

192.168.20.103

√Pass □No

2.4.4.2 Internet service test after switching

After switchover is completed, engineer will test Internet service according to table below and record test results.

Number

Test Content

Test results

1

Intranet test: web test, multiple test update

Baidu, Sina, Netease, Sohu

√Pass □Fail

2

Chat software test: QQ login test WeChat chat test

√Pass □Fail

3

P2P software test: a, Thunder

b, emule

√Pass □Fail

4

Test download speed: http download test

Thunder Boot Test

√Pass □Fail

5

Streaming media test: Youku test

LeTV test

√Pass □Fail

6

User Group Network Speed ​​Test: Leader Group, Information Group, Security Group

Security group, general group

√Pass □Fail

,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,, Chapter 3 Risk Management and Rollback Plan

3.1 Risks and Troubleshooting

Risk description

Phenomena Analysis

Troubleshooting steps

The aggregator management address is unavailable

Unable to access aggregation device via intranet management PC

1: Check that interface and device address are set correctly.

2: Check main switch port and IP settings.

3: Clear corresponding address entries in ARP address table.

The external network address R1 or R2 is not available

Unable to access external network resources

1. Check cable connection andport mode.

2. Turn off port f0/0 R1 or R2 and restart it.

3.2 Backup scheme

After pre-test time has elapsed, if you are unable to access Internet due to unknown issues, reset connection cable to its original state and roll back.

Chapter 4 Warranty after switching 4.1 Warranty requirements

In order to ensure a smooth switching operation, after switchover of flow control equipment, it is necessary to organize on-site warranty personnel to quickly fix problem as soon as it occurs and reduce business interruption time caused by error.

4.2 Personnel to switch

This switchover takes place in computer room 403, and on night of switchover, security personnel must be in computer room as follows:

Yong Bao Lu

Number

Company

People

Contact

Roles and responsibilities

1

Project interface employee

2

Interface

3

On-site project manager responsible for coordination

4

Implementation engineer responsible for changeover and warranty service

4.3 Warranty personnel

Number

Where to hide

People

Contact

Roles and responsibilities

1

Information Center

Coordination of solving urgent problems

2

Information Center

On-site project manager responsible for coordination

3

Information Center

Implementation engineer responsible for changeover and warranty

4.4 Warranty period

To ensure business continuity after switchover, partner will provide an 8-hour on-site visit and a 7*24-hour duty phone next day. If there is a problem during phone call, engineer will arrive on site within 2 hours.

Chapter 5 Optimization Scheme 5.1 Audit Function 5.1.1 Cause Analysis

According to current analysis of project's network access to external resources, there are many access content. To improve efficiency, some access elements are checked.

5.1.2 Optimization settings

According to need for intranet resources, configure devices according to best conditions.